February
is not an opportune time for certain kinds of work......
To
continue with the wall forms, the columns needed to be brought into the basement
prior to the closing off of the ramp by the concrete form.
All eighteen of the
columns had to be down and stored on the floor prior to enclosing the floor with
the concrete forms.
After the forms were up, there would be no way except by a
very large crane to lower the columns into the basement.
Here
are the columns in the previous year's bean field
David Weilbacher had brought
them to the farm on his bulldozer float.
As he turned the corner on the final
approach into the yard, the load shifted and everything rolled off the trailer and
into the cypress swamp.
David fetched his backhoe and he and Dean extracted them
from the morass.
They stacked them in the adjacent field; having no means to get
them back on the bulldozer float.
Weighing
about 3000 pounds each, it was necessary to jack them up with a 15-ton rail car jack.
Then
the ends were cribbed with oak four-by-fours high enough to back the lip of Dean's
trailer under the end.
Dean
would then attach a lever hoist and slowly slide the beast onto the trailer until
the center of gravity was in front of the front axle.
Then
they were hauled to the hole. Notice the column is longer than the sixteen foot trailer.
These
were the first floor columns.
Then
they would have to be backed around the windmill tower, past all the obstacles and
then down the bulldozer ramp.
Note the site manager in the foreground.
After
agonizing contortions (in reverse mind you), the trailer was backed down the ramp
and the column dragged off the trailer.
Once on the concrete floor, it was raised
and under it were placed two steel-wheeled carts.
Then a final chain hoist would
drag in the carts to a parking place.
The
three-ton chain hoist was mounted atop the doubled scaffolding.
Then
each column would be slowly and deliberitely lifted into place and bolted to the
floor.\
Oh great- another snow storm. No rest for the wicked.
View
from the sidewalk looking east. Notice the juniper tree lying on its side in the
basement.
Prior to this, torrential rains had wreaked havoc with the excavation
walls.
Finally, large portions of the walls collapsed into the hole.
This was
not limited to Dean. Excavators all around had the same problems that wet season.
The
six base columns have been erected with chain hoist and towers of scaffolding.
They
were bought down the ramp by loading them singly out in the field where they were
stored onto the tandem trailer.
Then with much difficulty the trailer was backed
down the earthen ramp used to drive out the bulldozer and dirt.
These weigh about
3000 pounds each and are very thick cast-iron.
The
six columns lying here now are the columns for the first storey; the basement columns
already having been installed.
The next storeys could not be installed until the
concrete foundation wall was poured.
This was because it was necessary to swing
a conctrete pumper boom and vertical columns would obstruct it.
Look at the column
end in the lower right-hand corner and notice the size of the opening.
Compare
that with the outer wall thickness and it is possible to understand how thick the
walls are and hence how heavy these pieces are.
Here
it is possible to see and understand that the scaffolding was double-ranked to increase
its carrying capacity.
Standard Patent scaffolding has a carrying capacity of
6000 lbs. per frame. That's 12,000 lbs per square.
Doubling them up gave an effective
rating of 24,000 lbs. capacity. OSHA requires 500% overage for overhead loads.
So
for 3,000 lbs, Dean was well within the safe range.
The other consideration was
that if one leg failed, the entire scaffold would fall over with only one leg per
corner.
With two legs per corner that risk was eliminated. That would provide
much easier breathing when the tower reach fifty feet tall.
The columns were fourteen
feet in the basement, sixteen feet on the first floor and fourteen feet on the second
floor.
That totals forty-four feet; hence the need for a fifty foot tower.
At
the top of the tower was the three-ton chain hoist with a hundred foot of chain fall.
That
was overkill, but everyone would exclaim how heavy and how impossible it must be
to lift those.
Consequently, Dean had his five year-old daughter hoist one up.
It's
all about preparation and mechanical advantage. Dean was able to set one column per
day.
It took six days to set the six showing. A crane would take a day, but would
cost $800.
Eight hundred dollars is a good week's wages, so it was a wash and
was in keeping with the principles of hand-construction.
The third and fourth
floors would be H-beam and I-beam construction.
In the original building the third
and higher storeys were 16" x 16" long leaf yellow pine timber beams.
These
lack some fireproof capabilities which was a concern.
Note the old dumptruck holding
up the maple tree from falling in the hole- a very grave risk given the rains.
Here
is the initial starting format for the wall forms. Here are three columns being formed
out.
When they are finished, the area in between will be paneled with laminated
4x4's.
Inside the forms are vertical, horizontal and diagonal 5/8's inch reinforcing
bar. About ten thousand pounds total.
Here
can be seen the initial installation of the laminated 4x4's on the exterior wall
of the form.
Note the dog guarding the ladder.
Here
is the opposite corner where the access to the ramp is about to be closed up.
Note
there is beginning to be some aerial storage. The red items are the floor joists
for the upper floors.